RED ELÉCTRICA DE ESPAÑA, S.A.U, within the Maintenance plan for 2014, plans to replace the conductors of a phase in a 220 kV circuit section Rubi – T. Celsa.
Power Line Features
- Voltage: 220kV
- Number of circuits: 1
- Support arrangement: Double Flag
- Number of conductors per phase: 1
- Conductor Type: Cardinal
Summary of work done
The actions carried out are:
- Transport of materials
- Conditioning access
- Protection of highway and road special crossings
- Removing existing conductors
- Laying of new conductors
- Hook, regulated and stapled conductors
- Restitution access and land affected